Custom perforated aluminum façade lead times vary by project complexity and production capacity but typically range from 6 to 10 weeks. The process begins with a 1–2 week design phase, where vector-based patterns are finalized and digital samples approved. Next, tooling and CNC perforation programming take another 1–2 weeks, during which custom die fabrication may be required. Coil-coating lines need batch scheduling; pre-treatment and finish application add 2–3 weeks. Final CNC profiling, perforation, and protective film application occupy the last 1–2 weeks. Expedited options—such as utilizing existing perforation patterns or in-stock alloys—can reduce lead times by up to 30 %. Early communication of design changes and proactive material sourcing help ensure on-time delivery.